System Design Overview
The System Design section is where you configure your HVAC systems, balance space airflows, design duct layouts, and review the resulting schedules.
Sections
Section titled “Sections”Configuration
Section titled “Configuration”Set up central unit and terminal unit equipment:
- Components on each unit’s airflow diagram: outside air, ERV, return air, coils, and fan heat
- Outside air method and supply air temperatures
- Energy configuration for energy estimates
- Design and required airflows at peak
Air Balancing
Section titled “Air Balancing”Balance each space’s airflows:
- Design supply, return, and exhaust
- Outdoor air delivered directly to the space
- Transfer air in and out
- The resulting differential, with a warning when the space is out of balance
Layout
Section titled “Layout”Design the duct distribution system:
- Register, terminal unit, and central unit placement
- Duct and riser routing and sizing
- Fitting loss coefficients: HVAKR places the fittings themselves
- Critical path and pressure calculations
Schedules (β)
Section titled “Schedules (β)”Review what the layout places, one table per schedule:
- Central Units and Terminal Units: name, area served, components, sizing airflows, and cooling and heating capacities. Terminal units also show the system that serves them
- Air Cleaners: the space, tag, linked product, manufacturer, model, description, and clean-air delivery rate (CADR). Change an air cleaner’s product or tag directly in the table. Selecting a product copies its tag; edit the tag for that unit, or clear it to remove the tag
- Registers: identical registers grouped by tag, type, placement, manufacturer, model, description, face size, and neck size, with a quantity
- Ducts & Fittings: length, fitting count, and sheet metal weight per duct type and size. Unsized ducts share one row per duct type, with no size, weight, or cost
Manufacturer, model, and description come from the linked catalog product and show its current values. A register without a catalog product shows the manufacturer and model of its register model, with no description.
A schedule with no items is hidden. Choose Costs in the header to show cost columns:
- Enter a cost for each central unit, terminal unit, and air cleaner. Register rows take a unit cost that applies to every register in the row and is multiplied by the quantity. Costs save on each item.
- Duct cost is calculated: the weight times the duct type’s Cost by Weight. Weight comes from the duct size, length, and the duct type’s Material and Wall Thickness, set under Basis of Design > System Types. Fittings are counted but not priced.
To export a schedule, select its rows and choose Download CSV in the selection toolbar.
Workflow
Section titled “Workflow”The typical system design workflow:
- Configure - Set central unit and terminal parameters
- Balance - Adjust per-space supply, return, exhaust, and transfer airflows
- Layout - Route ducts and size components
Each step builds on the previous, so work through them in order.
System Configuration
Section titled “System Configuration”Before designing ductwork:
- Verify system loads are accurate
- Set appropriate supply air temperature
- Configure outdoor air requirements
- Add the components each terminal unit has
Design Validation
Section titled “Design Validation”Run the project Check to validate your design: ask AI Chat to “Check this project,” or run a check job via the REST POST /projects/{id}/jobs endpoint. Check’s design-quality checks include:
- Airflow balance: central unit and terminal (zone) supply vs. return/exhaust
- Equipment oversizing: coil capacity flagged when it’s more than 200% of peak load
- CFM/ton ratio outside the expected 300–500 range
- Duct heat gain coverage against the ceiling-plenum cooling load
Check skips the oversizing and CFM/ton checks for a system whose central unit supplies 100% outside air (a DOAS). That unit’s airflow and coil capacity follow the ventilation air, not the space load.
Best Practices
Section titled “Best Practices”- Finalize loads first - Complete building model before system design
- Work system by system - Focus on one system at a time
- Check air balance - Verify supply equals return plus exhaust
- Validate equipment - Confirm selected equipment meets requirements
- Document assumptions - Note design decisions for future reference